OUR PROCESS

OUR TURNKEY process WILL HAVE YOUR TANK READY TO USE IN LESS THAN 6 MONTHS.

Fathom Tank Installation is Fast and Reliable.

DESIGN 2-3 DAYS

  • We work with your team to design a water simulation tank that suits your requirements.
  • You receive a CAD drawing of your tank and all parts before fabrication begins.
  • We can assist your site developers with architectural renderings for permitting.
1
2

FABRICATION 12 WEEKS

  • Tanks are constructed of bolted-metal sheets.
  • Fabrication takes 1-3 months depending on the complexity.
  • Completed tanks arrive ready to assemble at your location.

ASSEMBLY4-6 WEEKS

  • Fathom’s team will arrive to assemble your simulation tank.
  • Tanks are filled, tested for leaks, drained and tested again.
  • Lastly, tanks are coated with a 3mm layer of leak sealant.
3
4

STAGING1-2 DAYS

  • Simulation tanks and all equipment are ready to use immediately.
  • Heating water takes 1-4 days to complete, depending on depth.
  • Training props are installed and secured.

USE FOR TRAINING & RESEARCH

Tanks can be used to offer endless types of training, such as: swiftwater and flood rescue training, scuba diving and surface supplied air diving, university or collegiate testing, aerospace training, and more.

5

USE FOR MEDIA PRODUCTION

Tanks can be used to simulate various water locations and underwater environments for media production. Simulate dangerous water situations in a safe, controllable location.