DEVELOPMENT TIMELINE
LET US BUILD A FATHOM
TRAINING TANK FOR YOU.
Fathom tank construction is fast and reliable.
DESIGN 2-3 WEEKS
- We work with your team to design a training tank that suits your requirements.
- You receive a CAD drawing of your tank and all parts before fabrication begins.
- We can assist your site developers with architectural renderings for permitting.
1
2
FABRICATION 12-18 WEEKS
- Tanks are above-ground and constructed using bolted-metal sheets.
- Fabrication takes 4-6 months depending on the complexity.
- Completed training tanks arrive in several 40ft shipping containers.
ASSEMBLY4-6 WEEKS
- Fathom will accompany the tank and parts arriving from our fabricators.
- Assembly takes 4-6 weeks, but will increase depending on the complexity.
- Bolted panels are water-tight with gasket seals.
3
4
TURN-KEY1 DAY
- Tanks fill with water in 1-2 days; slightly longer depending on the size.
- Filtration works immediately; heating can take as long as 4 days to complete.
- Pumps are controlled by variable frequency drives to allow for total control.